|
Status: 20 November - Moving in commences
17
November - Temporary Occupancy Certificate
28 June Interior framing complete
15 June, Exterior, floor & outside plumbing finished!
24 May, Roofing Starting.
10 May, Sheeting Started.
26 April, First Steel Erected.
24 April, Foundation
Finished.
17 April,
First Concrete Poured
April 2006 Building Permit
Acquired
|
|
|
|
|
|
|
|
The building arrives on one flat bed truck. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Then there was more excavation. |
|
|
|
|
|
|
|
|
|
|
|
|
Then the holes had to be filled back in with packable ground. |
|
|
|
|
|
|
|
|
|
|
|
|
The ground is ready for a foundation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Phone cable had to be moved. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Pouring the foundation pads |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pouring the Foundation Wall. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bolts to attach Steel to foundation. |
|
|
|
|
|
|
|
|
|
|
|
|
Foundation wall being backfilled. |
|
|
|
|
|
|
|
|
|
|
|
|
First Steel Beam in place. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Securing the Steel beams. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Piles of Fill & Insulation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Garage Doors being set and Roof starting. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Never rains here. 10 X 5 X 10 hole 3/4 full of water. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Shop is ready to service Corvettes and ... |
|
|
|
|
|
|
|
|
|
|
|
|
Lifts to convenently work on them |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ready to move in Accessories |
|
|
|
|
|
|
|
|
|
|
|
|
|
Frame ready for powercoating. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Corvettes for Sale in the Showroom. |
|
|
|
|
|
|
|
|
|
|
|